- American Transmission Company (ATC) refiled its application with the Public Service Commission of Wisconsin (PSC) in September 2026 after the commission withdrew its initial completeness finding, restarting the clock on the transmission link serving Oracle's Project Lighthouse campus in Port Washington.
- Research firm Aterio framed three regulatory trajectories for the campus, which draws 902 MW of computing load and 1.3 GW of total electricity demand.
- Even if the PSC approves ATC's filing by December 2027, each building must still undergo electrical and cooling system testing, commissioning and load ramp-up before it can carry customer traffic.
Selected from this article · 2026-10-03
Read on for the full pictureRegulatory restart puts the Wisconsin delivery window at risk

American Transmission Company (ATC) refiled its application with the Public Service Commission of Wisconsin (PSC) in September 2026 after the commission withdrew its initial completeness finding, restarting the clock on the transmission link serving Oracle's Project Lighthouse campus in Port Washington. The PSC review must clear before ATC can begin construction on the lines and substations needed to deliver power, and ATC has earmarked more than $2 billion in Wisconsin transmission projects tied to multiple datacenter developments, covering high-voltage lines, substations and upgrades to existing facilities. The same PSC proceeding governs that interconnected build, so any delay propagates across competing projects.
Aterio's three scenarios narrow the path to a 2027 deadline
Research firm Aterio framed three regulatory trajectories for the campus, which draws 902 MW of computing load and 1.3 GW of total electricity demand. Its highly unlikely best case delivers partial power in October 2027 and full supply in August 2028; its base case shifts first power to December 2027 with full supply in October 2028; an extended review could push partial power to June 2028 and full supply to April 2029. Aterio warned that "the regulatory record points to the potential for dates later than company guidance, and Oracle's stretched finances, together with its force majeure notice on Project Jupiter in New Mexico this week, raise the potential for slippage on its largest campuses." Only the highly unlikely scenario aligns with Oracle's H2 2027 customer delivery target, and even that window leaves little room for testing.
First power is not customer-ready capacity
Even if the PSC approves ATC's filing by December 2027, each building must still undergo electrical and cooling system testing, commissioning and load ramp-up before it can carry customer traffic. Aterio expects operational capacity at the campus to ramp mainly from the first quarter of 2028, a cadence that compresses Oracle's H2 2027 customer delivery goal to near zero under the base case. Financing guarantees behind the power commitments could cost Oracle more than $100 million a year, a figure carried by The Register's reporting.
Project Jupiter notice links Wisconsin to broader portfolio strain
Separately this week, Oracle issued a force majeure notice to a Blue Owl Capital subsidiary developing Project Jupiter in New Mexico, seeking to defer payments if that campus fails to come online as planned, though Oracle has said Project Jupiter remains on schedule. Aterio's note ties the New Mexico stress to Wisconsin timing, arguing that Oracle's stretched finances amplify slippage risk across its largest campuses. The combined signal indicates Oracle is managing contingency exposure on simultaneous datacenter deliveries, with grid approval in Wisconsin acting as the binding constraint.
Bounded uncertainty hinges on PSC scheduling and testing cadence
The next verifiable milestone is the PSC's completeness determination on ATC's refiled application, which will reset the formal review window. A separate open question is whether Aterio's base case of partial power in December 2027 can accommodate the testing and commissioning cadence Oracle's H2 2027 customer delivery commitment assumes; the firm's modeling shows a clean approval still leaves the original deadline unmet. Resolution depends on PSC scheduling decisions and on Oracle's ability to absorb financing and force majeure exposure on parallel campuses, outcomes the available evidence does not yet resolve.